Worked example: a shelving job with a loose end
Fictional job CW-104. Avery and Morgan were assigned a floor clean and assembly of two shelving units. They cleaned the floor and assembled one unit. The second box was missing hardware. The customer also requested wall mounting, which was outside the approved scope.
The crew records one unit assembled, the missing hardware and the wall-mounting request without marking those tasks complete. The office owns the return-visit decision and checks it by the next business morning. The invoice draft needs review against the approved arrangement; neither a full charge nor a discount should be inferred from the completion button alone.
The closeout is useful because the next person knows exactly what remains. A vague “done, customer happy” note would conceal the unfinished unit and the unapproved addition.